栅槽埋件的安装 1. 栅槽的安装采用特制的自升、自锁式钢吊笼供施 工人员上下作业和装载工具器及安装材料等。 2. 栅槽安装穿插在混凝土浇筑的层间和分段 间隙进行,当混凝土浇筑到满足门槽埋件安装的条件时,进行门槽埋件的安装。 3. 栅槽安 装时, 首先要引进门槽安装所需要的高程、 里程及门槽基准点, 根据基准点焊接所需要的线 架,悬挂钢琴线,为安装作好一切准备工作。 4. 准备就绪后就可开工。先装底槛,底槛吊 到位后, 利用调节螺栓和千斤顶进行调节, 使各控制尺寸符合设计图纸及规范的要求, 尺寸 合格后对底槛进行焊接加固, 底槛进行可靠加固后, 继续进行其余门槽安装, 对尺寸复测并 记录, 复测的尺寸合格后填表报请监理人验收。 验收合格后, 交土建进行二期砼的浇筑。 5. 二期砼浇筑完成, 向混凝土工程交面前, 作保护栅栏, 有效保护浇筑好的栅槽埋件在混凝土 施工中不被损坏。 6. 待混凝土浇筑到可以进行上部埋件安装时, 进行上部栅槽埋件的安装。 如此循环,直至安装完所有栅槽埋件。 7. 全部埋件安装完毕后,对栅槽埋件和锁定梁轨道 整体进行打磨、清理,并复测整体尺寸,包括扭曲度、不平度和错位情况,合格后填表报请 监理人进行栅槽埋件的整体验收。 The installation of grid groove embedded parts is installed in 1. grid slots. The special self elevating and self locking steel suspension cage is used for the upper and lower work of construction personnel and loading tools and installation materials. The 2. gate slot installation is inserted in the interlayer and section gap between the concrete pouring, and when the concrete is poured to meet the conditions of the installation of the buried parts of the gate, the installation of the buried parts of the gate slot is carried out. When the 3. gate is installed, the height, mileage and the datum point required for the installation of the gate must be introduced first, and the piano line is suspended according to the required wire frame of the base point welding, and all the preparations are made for the installation. 4. will be ready to start when it is ready. First the bottom sill, after the sill hoist is in place, the adjustment bolts and jacks are used to make the control dimensions conform to the requirements of the design drawings and specifications. After the sill is qualified, the sill is welded and strengthened. After the sill is reliably reinforced, the rest of the door slots are continued to be installed, the dimensions are remeasured and recorded, and the remeasured dimensions are qualified after filling the form. Report to the supervisor for acceptance. After acceptance, the construction of the two stage concrete will be carried out. 5. the two stage concrete pouring is completed, and the protection fence is made before the concrete works are delivered, so as to effectively protect the well grooved embedded parts from being damaged in the concrete construction. 6. when the concrete is poured into the upper part, the installation of the upper grid slot can be carried out. It is so circulatory until all the grate buries are installed. 7. after the installation of all the buried parts, the overall size of the grate buried parts and the track of the lock beam is cleaned and measured, including the distortion, unevenness and misplacement. The qualified post fill is reported to the supervisor for the overall acceptance of the gate buried parts.
网站建设及优化:保定遨游公司 版权所有 © 河北省衡水市顺益水工机械厂
联系人:南经理 手机:13932899771 电话/传真:0318-8832626 邮箱:706843811@qq.com 地址:河北省冀州市西王工业区
水利机械推荐:启闭机、螺杆启闭机,卷扬启闭机、启闭机闸门、铸铁闸门、钢制闸门、清污机、拦污栅、橡胶止水等 网址:www.qibiji58.com
友链:光纤激光切割机 抹灰机 螺杆启闭机 过电压保护器 隔离墩模具 蠕动泵 启闭机 电缆挂钩 铸铁闸门 精密铸造 光纤激光切割机 造型机 网站建设及优化:保定遨游公司